Phi5600 Installation Photos

day 01
Day 1: No monochromator. Lots of cardboard. Base pressure 7.6E+2 Torr.
day 03
Day 3: Main chamber pumping. High pressure cell in progress. Base pressure 2.2E-5 Torr.
IMG_4746 Day 3: Sample stage and puck. Looking through 4.5" Conflat viewport. Base pressure 2.2E-5 Torr.
Day 3: Sample stage and puck. Looking through 4.5″ Conflat viewport. Base pressure 2.2E-5 Torr.
day 04
Day 4: 150 °C bakeout, or a cold day in New England. Base pressure 3.5E-6 Torr.
day 06
Day 6: Everything is together. Dealing with leaks. Base pressure 2.0E-8 Torr.
day 09a
Day 9: X-rays are hitting the phosphor! The twin anode light hits everything. Base pressure 9.0E-9 Torr.
day 09b
Day 9: X-rays from the monochromated aluminum source give a small spot. Base pressure 9.0E-9 Torr.
day 10
Day 10: Aligned and ready to go! Anyone for dataing? Base pressure 5.8E-9 Torr.